16.35

FINANCIAL SAVING

$953 (USD)

CO2 SAVING

8844 lbs

The performance of EndoTherm was piloted by Cardiff Metropolitan University at the Llandaff N Block building in Cardiff, UK.

The site is powered by three 115kW Purewell boilers and EndoTherm was installed in September 2017.

Baseline

To run a successful trial on any energy saving technology a comparison period or baseline must be established, this case study follows the guidelines set by the International Performance Measurement & Verification Protocol (IPMVP). Cardiff Metropolitan University has gas consumption data accurate to 30‡ƒ minute (half hourly) intervals. It is noted that the building is heated in line with use (Monday to Friday) and heating is turned off at weekends.

Comparison

For each month the data from 2016/17 was compared to the same month in 2017/18 using IPMVP protocols. The table below includes compensated heating degree day (HDD) data from a nearby weather station located in Cardiff.

The savings can be quantified by calculating the predicted usage (using the 2016/17 usage data) and the HDD value for each day is used. Predicated usage is then compared with actual usage to identify savings realised each day, the total saving for the monitored period is then calculated by using a cumulative sum (CUSUM) of every daily saving.

 

Results

Time Period Predicted Usage (kWh) Actual Usage (kWh) Usage Difference (kWh)
October 2017 16,808.41 13,237.56 3,570.85
November 2017 23,568.35 20,347.38 32,20.97
December 2017 37,875.6582 34,367.3 3,508.36
January 2018 54,445.3122 42,892.55 11,552.76
Total 132,697.73 110,844.8 21,852.94

 

Savings

Compensated Saving:

16.35%

Total Cash Saving:

$953 (USD)

Total CO2 Saving:

8844 lbs

 

Contact Us

Permission to contact:

BEIC September 2019 Newsletter. EndoTherm success at the University of the Fraser Valley

Following the publishing of the EndoTherm case study at Vancouver Airport (click here) on the Building Energy Innovators Council (BEIC)'s website. The success of EndoTherm at the...

Case Study Spotlight: 850 King St – Grand River Hospital

Following last weeks spotlight at 200 Rue Montcalm (for more info click here); the first heat pump pilot in North America and first commercial pilot in Quebec, we have the pleasure of...

Building Energy Innovators Council (BEIC) re-publishes EndoTherm pilot at Vancouver International Airport

The Building Energy Innovators Council (BEIC) have recently re-published the case study of EndoTherm Pace Chemicals ran at Vancouver Airport. The BEIC was founded in 2016 by a diverse...

Case Study Spotlight: Multivesco

This weeks case study spotlight focuses on the recent success of real estate development company; Multivesco. The proof of concept EndoTherm pilot, run at their head office (200 Rue...

Adey Confirm Compatibility between EndoTherm and MC1 Protector Range

EndoTherm has today confirmed compatibility with Adey's leading line of corrosion inhibitors MC1 Protector and MC1+ Protector. This follows similar approvals from Sentinel and...